RMC Switchgears: Disclosure For Material Information As Regulation 30 Of SEBI LODR 2015 Regarding Contract Awarded

Pursuant to the requirements of Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations 2015 [abbreviated as SEBI (LODR)] particularly Regulation 30 requiring the notification of material events we are pleased to notify the Bombay Stock Exchange (BSE) regarding a significant work order awarded on 12.07.2024 to the company for supply and installation of solar equipment a 220 KV substation and a 5 km transmission line material for a 25 MWac ground mount solar plant with a single-axis tracker in Bhuj Gujarat.The value of work order is approx. Rs. 86.48 Crores (including GST).